| ASU Breakdown at
Bhilai Steel Plant Bhilai
Steel operated 2 x 550 TPD Oxygen ASU for feeding oxygen to their steel making furnaces.
One of the ASUs suffered a breakdown, which severely affected the operation of the LD
Converters causing loss of crores of rupees per day. The fault was diagnosed as leakage in
the Reversing Heat Exchangers (RHE) of the ASU. The ASU had been supplied by BHPV, and the
RHE was of KOBE Japan make. Getting replacement from KOBE would take months, and in
the meanwhile the production of steel would be severely affected a situation that
spelt doom for the Steel Plant. BSP approached BOCI for help.
Even though the plant in question
was a competitor supply, BOCI swung into action to help out a valued Client in distress.
Specialists in heat exchanger repairs including BOCIs specially trained welding
engineers, technicians etc., were flown in within 24 hours to check the feasibility of
repairing the exchangers in-situ. Materials required for repairs were diverted from BOCI
running project sites, and flown in to BSP for the repairs. Round the clock work was
undertaken, and repairs completed, and the ASU put back in operation within seventy-two
hours of the breakdown.
Ship Superstructure fabrication
at Hooghly Dock & Port Engineers Limited
Hooghly Dock & Port
Engineers Limited (HDPEL) had a contract from the Andaman Port Trust Authority for
construction of a 100Ton-cargo cum 400-passenger ship. The ship of modern design was to be
constructed with Aluminium Superstructure a first for HDPEL who had never
undertaken any Aluminium fabrication works before, and needed a competent contractor to
outsource the construction of the Ship Superstructure.
BOCI through their extensive
experience of Aluminium fabrication & welding garnered through years of ASU
installation involving Aluminium construction of Columns, Main Exchangers, Cold Box pipe
work etc., was uniquely placed to service this critical requirement of HDPEL. BOCI had
never undertaken ship construction before but BOCIs engineers promptly took
up the challenge, and the construction of a magnificent luxury liner at Hooghly Dock is
now in progress, where Contracts Division is yet once again proving its ability to deliver
a quality job under the strict quality control of Lloyds to the entire satisfaction of the
Client.
Construction of Tocomak at
Institute for Plasma Research, Gandhinagar
Institute for Plasma Research
(IPR) at Gandhinagar was set up under the Department of Science & Technology with the
objective of producing plasma a hitherto uncharted territory in the annals
of Particle Physics Research in the country. The main challenge was to develop and install
a super-conducting tocomak for the first time in the country. The construction of the
tocomak involved extensive installation of triple jacketed liquid helium transfer lines,
valve boxes & cryostats with liquid nitrogen shielding, required for the
super-conducting current leads for the tocomak. In addition, an extensive liquid nitrogen
distribution & control system for cooling of the radiation shields, involving vacuum
jacketed liquid nitrogen transfer lines was also required for the system.
BOCI had earlier developed similar
liquid helium & nitrogen systems, albeit on a much smaller scale, for the first time
in the country for the LINACS (Linear Accelerator) Project of Nuclear Science Centre (NSC)
at Delhi. After review of the impeccable job done by BOCI at NSC, IPR decided to do away
with expensive & difficult (due to restrictive export policy of the supplier
countries) import of such systems, and relied on BOCI to deliver this critical sub-system
of the tocomak. Yet another challenge which Contracts Division has taken in its stride,
and is confident of concluding successfully.
Helium Recovery from Geothermal
Springs
Department of Science &
Technology (DST) was looking at means to exploit the gas emanating from geothermal springs
at Bakreshwar in West Bengal, for extracting helium. The gas from these springs contained
approx 1% helium, and the requirement was to develop a feasible process for extracting
crude helium up to 90% purity. If successful this would be the first indigenous source of
helium in the country. DST operating through the Variable Energy Cyclotron Centre (VECC),
and Saha Institute of Nuclear Physics (SINP) in
Kolkata, approached BOCI for
participating in this crucial technology development program, which would go a long way in
making the country self sufficient in helium.
BOCI took up the challenge, and
process engineers after extensive study, developed a design using cryogenic separation
process for removal of impurities and extract 90% pure helium from the feed gas. BOCI then
went on to create a prototype a pilot plant was set up in VECC
Kolkata, which
after undergoing rigorous trials validated the design developed by BOCI. A process to
further purify the product to 99% Helium using molecular sieve adsorption technology, is
being currently examined by BOCI and VECC / SINP. |